Project Progress
DESANDER (SETTLING BASIN)
Settling basin foundation and shear wall reinforcement as well as concreting work progress is around 80%. Remaining works in desander will be finalized during rainy season.Total budget of this section including Head pond according to BOQ is Rs 3,77,45,682/- including VAT and total estimated work progress at this section till date is of around Rs 2,64,22,592/-
APPROACH CANAL, INTAKE, GRAVEL TRAP, SPILL WAY CANAL
For the construction of remaining approach canal and bell mouth, gravel trap, spill way canal at intake, the excavation work is done. Reinforcement and concreting work for this section will be executed during monsoon. Moreover, to increase the height of existing canal by 1.5m, chipping and reinforcement work is in progress. In addition to this, considering the road conditions during monsoon, the total requirement of rebar is stocked at site. Total budget of this section according to BOQ is Rs1,93,08,779/- including VAT and total estimated work progress at this section till date is of around Rs 32,00,000/-.
WEIR, UNDER SLUICE AND INTAKE
Till the end of May 2017, Earth work excavation for the foundation of under sluice and flood wall is completed, about 90% of civil works including foundation and shear wall reinforcement as well as concreting works at under sluice portion is completed. Total budget of this section according to BOQ is Rs6,34,92,810/- including VAT and total estimated work progress at this section till date is of around Rs 4,92,00,000.00.